NNHPD Performance Standards

Posted Date: 7-October-2025

NNHPD Consultation on Two New Monographs

 

PRODUCT LICENSING:

 

The NNHPD has returned to meeting its performance standards for new and post-licensing Class I and II applications. There are approximately 4150 files in Class III (4130 in August) (this includes new and post-licensing files that are in queue and working), of those approximately 900 (840 files August) are past the 210-day service standard.

 

  • Screening files at approx. 130 -160 days (110 – 140 days August)
  • Assessing files at approx. 240 days (220 days August)
  • Issuing decisions at approx. 260 days (270 days August)

 

 

SITE LICENSING:

 

New Applications:

 

Stream 1: Site Clock Day 10 received as of September 2025 (Site Clock Day 10 received as of August 2025)

Stream 2 or Stream 3: Site Clock Day 54 received as of July 2025 (Site Clock Day 54 received as of June 2025) 

 

Amendments:

 

Stream 1: Site Clock Day 15 Received as of September 2025 (Site Clock Day 22 received as of August 2025)

Stream 2 or Stream 3: Site Clock Day 49 received as of July 2025 (Site Clock Day 46 received as of July 2025)

 

Renewals:

 

Stream 1: Site Clock Day 16 received as of September 2025 (Site Clock Day 15 received as of August 2025)

Stream 2 or Stream 3: Site Clock Day 52 received as of July 2025 (Site Clock Day 54 received as of June 2025)