NNHPD Performance Standards

Posted Date: 15-July-2025

NHP Product and Site Licence Performance Standards

 

PRODUCT LICENSING:

 

There are approximately 3980 files in Class III (3712 in June) (this includes new and post-licensing files that are in queue and working), of those approximately 795 (605 files June) are past the 210-day service standard.

 

  • Screening files at approx. 110 -140 days (150 – 160 days June)
  • Assessing files at approx. 220 days (240 days June)
  • Issuing decisions at approx. 275 days (265 days June)

 

 

SITE LICENSING:

 

 

Stream 1: Site Clock Day 15 received as of June 2025 (Site Clock Day 14 received as of May 2025)

Stream 2 or Stream 3: Site Clock Day 50 received as of April 2025 (Site Clock Day 43 received as of March 2025) 

 

 

Stream 1: Site Clock Day 17 Received as of May 2025 (Site Clock Day 15 received as of May 2025)

Stream 2 or Stream 3: Site Clock Day 44 received as of May 2025 (Site Clock Day 44 received as of April 2025)

 

 

Stream 1: Site Clock Day 25 received as of May 2025 (Site Clock Day 20 received as of May 2025)

Stream 2 or Stream 3: Site Clock Day 47 received as of April 2025 (Site Clock Day 44 received as of January 2025)